Hospital Project

Tinto Hospital Triage And Stabilization (TAS) Unit

                            Cost Estimate

 

Approximate surface area: 150 square meters

 

1- Cost of material: 135,000 F/sq.m x 150 sq. m          =                20,250,000 F cfa

2- 10 % overhead (transportation and unforeseen)      =                2,025,000

3- Total cost of material                                                 =                22,275,000

4- Labor 25% of total cost of material                           =                5,568,750

5- Total cost (material + labor)                                      =                27,843,750

 

Costs according to phases of work execution

 

A- First phase

a. Foundation to Damp Proof Course (DPC) + Septic Tank and soak-away

i) Material 2/10th                =           4,455,000

ii) Labor 1.9/10th                =           1,058,063

 

B- Second Phase

a. Elevation + Roofing + Electrical and plumbing conduits

i) Material 3.3/10th              =          7,350,750

ii) Labor 3/10th                    =          1,670,625

 

C- Third Phase

a. Flooring, Ceiling, carpentry, painting and other fittings

i) Material 4.7/10th               =        10,469,250

ii) Labor 5.1/10th                  =        2,840,063

 

 

 

Equipments