Hospital Project
Tinto Hospital Triage And Stabilization (TAS) Unit
Cost Estimate
Approximate surface area: 150 square meters
1- Cost of material: 135,000 F/sq.m x 150 sq. m = 20,250,000 F cfa
2- 10 % overhead (transportation and unforeseen) = 2,025,000
3- Total cost of material = 22,275,000
4- Labor 25% of total cost of material = 5,568,750
5- Total cost (material + labor) = 27,843,750
Costs according to phases of work execution
A- First phase
a. Foundation to Damp Proof Course (DPC) + Septic Tank and soak-away
i) Material 2/10th = 4,455,000
ii) Labor 1.9/10th = 1,058,063
B- Second Phase
a. Elevation + Roofing + Electrical and plumbing conduits
i) Material 3.3/10th = 7,350,750
ii) Labor 3/10th = 1,670,625
C- Third Phase
a. Flooring, Ceiling, carpentry, painting and other fittings
i) Material 4.7/10th = 10,469,250
ii) Labor 5.1/10th = 2,840,063
Equipments